Introduction
A contract is usually discharged when both parties have performed all of their obligations under the agreement and thus both parties have fulfilled what they promised to do at the very outset of the contract. There is a distinction to be drawn between the discharge of a valid contract and the ways in which invalid contracts come to and end. This article assumes that a commercial contract has been properly formed and one of the parties wishes to terminate the contractual relationship.
Bring a Contract to an End
There are four ways in which a contract may be discharged.
1. Discharge by performance
Discharge by performance is where both parties to a contract have performed all their primary obligations under the contract, including all express and implied terms. There are three elements required to be satisfied to say, at law, that performance is complete.
Each of the parties is required to perform their obligations under the contract with perfect precision. Any deviation from the contractual obligations will amount to a breach of contract. In the case of Bolton v Mahadeva (1972), it was held that a contractor could not claim payment for a central heating system which did not work properly as it did not fulfil the primary obligation of heating the house. On the other hand, sometimes performance is not strict and the obligation is not to achieve a specific result, but merely to exercise reasonable care and skill.
Where a contract requires strict performance there are circumstances in which the law will allow payment for part performance of a contract or incomplete contracts on a quantum meruit basis which enables the party performing to get paid fair and reasonable remuneration for their work where:
(i) the contractual obligations are divisible, payment can be recovered for the obligations completed.
(ii) partial performance has been accepted by the other party.
(iii) the other party prevents complete performance by a party ready willing and able to perform.
(iv) a substantial part of the contract has been completed.
Tender of performance takes place when a party attempts to perform their primary obligations under the contract and is prevented from doing so by the other party. It is this that discharges the parties’ obligations. Where a party tenders performance which is refused by the other party, they may sue for breach of contract. Where a party tenders payment, the obligation to tender payment is discharged, but the debt itself isn’t, so even if payment is rejected, the party is still obliged to pay.
2. Discharge by agreement
A contract may be discharged by agreement in various situations:
Where both parties consent, the mutual obligations to perform contractual obligations will come to an end. Where a contract is discharged in this way, as with any contract, the agreement must be supported by consideration be legally binding. Where both parties have performance obligations outstanding under a contract, an agreement between the parties to discharge those obligations will be enough to satisfy the requirement for consideration, making it legally binding.
However, where one party still has performance obligations under the contract, for the agreement to be legally binding there must be either:
(i) A deed releasing the other party from their obligations; or
(ii) A separate agreement supported by new consideration (‘accord and satisfaction’); or
(iii) The Doctrine of Promisory Estoppel must apply, that is to say where a promise is made, intended to be binding and acted upon, the court will uphold the promise.
It is always open to parties to agree to variations of a their contractuals arrangements. This is put in place by executing a new agreement which supplements the first (rather than entirely replacing it). In some circumstances, the original contract may be discharged in its entirety and replaced with a completely new contract. In either of these circumstances though, the existence of a separate agreement must be proved. Accordingly, it should be in writing.
A contract may be discharged by a condition subsequent which is a stipulation of a state of affairs which causes existing contractual obligations to come to an end. The state of affairs does not necessarily have to be out of the control of the parties.
3. Discharge by breach
When a breach of contract takes place, it does not automatically discharge a contract. If the breach amounts to a breach of a condition of the contract, the innocent party has the option of either accepting the breach, terminating the contract (which has the effect of discharging the parties from any further obligations under the contract) and suing for damages; alternately simply sue for damages caused by the loss caused by the breach, this allowing the contract to continue in force. Where the failure to perform amounts to a breach of warranty, the innocent party is not entitled to terminate the contract, but simply sue for damages.
There are situations in which the innocent party wrongly treats the contract as repudiated by the party in breach, and purports to terminate the contract. This is repudiation of the contract by the innocent party for non-repudiatory breach and is a breach of contract in its own right, entitling the other party to treat the contract as discharged. This was demonstrated in the case of Federal Commerce and Navigation v Molena Alpha (1979) where the owners of a ship wrongly believed they were entitled to repudiate the contract. The court held that the repudiation was wrongful and therefore the other party could treat the contract as discharged.
Where a contract is treated as discharged, the performance obligations under that contract are discharged at the date of termination. However, performance of secondary obligations, namely the obligation to pay damages for any losses caused to the innocent party, are not discharged and continue in force.
Anticipatory Breach
An anticipatory breach of contract may be either explicit or implicit. Such takes place where one party expresses an intention by either not performing their obligations under the contract or performing them in a way in which is inconsistent with the original contractual terms. In these circumstances there are a number of options available to the innocent party. They may sue for damages as soon as the anticipatory repudiation occurs, there do not need to wait for the date of performance.
The innocent party also has the option of either accepting the repudiation by the other party, thereby terminating the contract, or affirming the contract by performing their obligations under it. In the case of White and Carter Limited v McGregor (1962), the defendants cancelled the contract, but the claimants refused to accept the termination and continued with performance under the contract, later suing the defendants for the full contract price. It was held that the claimants were entitled to do this.
The option of accepting the repudiation or terminating the contract is not available where the innocent party requires the cooperation of the other party to perform the contract or if they have no real interest at all in performance of the contract.
4. Discharge by frustration
Discharge by frustration occurs where it is impossible to perform the obligations under a contract due to a subsequent change in circumstances. It is the nature of the obligations which must have changed.
The modern test for frustration is outlined in the case of National Carriers v Panalpina (1981). Frustration occurs when “ .. there supervenes an event (without default of either party and for which the contract makes no sufficient provision) which so significantly changes the nature (not merely the expense or onerousness) of the outstanding contractual rights and / or obligations from what the parties could reasonably have contemplated at the time of its execution that it would be unjust to hold them to the literal sense of its stipulation in the new circumstances.”
Frustration may occur in a number of situations:
The Doctrine of Frustration will not apply when:
a. simply because an inconvenience has been caused, there has been an increase in expense or loss of profit. In Davis Contractors Limited v Fareham UDC (1956), it was agreed that a council estate would be built at a fixed price, but due to bad whether, strikes and shortages there were delays and the estate was built at a loss. However, it was held that the contract was not frustrated.
b. the contract contains an express provision (force majeure clause), dealing with such eventualities.
c. frustration is self-induced and one of the parties had a choice regarding performance.
d. the event was reasonably foreseeable by either party as at the date of the agreement.
Conclusions
We have set out the fundamental ways and means by which a contract may be brought to an end. Professionally drawn contracts may contain other means by which the contract may be brought to an end without suffering loss, such removing any rights to damages or recovery for loss, providing for termination for convenience of a party, warranties that presuppose a state of affairs as at the time of the contract that has not eventuated. Moreover, damages claims may be limited to specified sums or avoided in their entirety provided the innocent party does not fulfil their duty to mitigate their loss in the circumstances.
Contract Terms – Briefing Note - Outsourcing Services – Key Considerations
Contract Terms – Checklist for Software Licence Agreements - Software Licence Agreements and Software Development Contracts
Regulatory Compliance – Regulatory Compliance Briefing Note - Implied Terms in Business Contracts for the Sale of Goods
T: +44 20 7353 2732
F: +44 20 7353 2733
Email Us
Contact our lawyers online

Sitemap
Technology | Commercial | Corporate law firm | London UK
Solicitors & Lawyers | Copyright | Gillhams 2005 - 2008

